BRIDGE ACROSS KING’S DOCK AT KEPPEL HARBOUR

Country: Singapore
Client:  Harbourfront Three Pte Ltd
Main contractor: Who Hup (Pte) Limited
Start date:  September 2014
End date:  August 2015

Scope:  6 x 1300mm dia marine bored piles
87m x 6.8m bridge
Post-tensioning
600m3 ready mix concrete
50m long centre span
granite tiles
Stainless steel railings

Challenges:  Obstruction to land piles from old dock walls
Adjacent operational Cruise Terminal