RETAIL MALL CONVERSION AT MARINA BAY SANDS

Country: Singapore

Client: Marina Bay Sands

JV Partner: McConnell Dowell South East Asia Pte Ltd

Start date: September 2017

End date: January 2019

Scope: Demolition of building including removal of 750ton steel, 3,000m2 of glass and 3,500m3 of concrete.
Construction of a 230m long cofferdam
Installation of 25 piles
RC structure to 650ton of steel and 2,500m3 of ready-mix concrete.

Challenges:  Site in proximity of Mall and retail outlets
Multiple underwater obstruction to sheet-piles
Structure connected to existing Mall through a   tunnel. Risk of flooding
Marine logistics with limited plants.