REMOVAL OF DAMAGED MOORING DOLPHIN (MD4) AT JETTY 6/7 BANYAN

Country:   Singapore

Client:  VOPAK TERMINALS SINGAPORE Pte Ltd

Start date:  04 September 2020

End date:   23 September 2020

Scope:  Removal of Damaged Mooring Dolphin Structure Consisting of:
7mx7mx2.5m (~300T) Concrete Structure
And 8 nos of OD800mm Raked Piles

Challenges:  300T concrete structure sheared off at pile connection, unstable condition.
Safety of personal working near unstable structure.

Overcome by:  Mobilised 1200T Floating Sheerleg with 600T capacity hydraulic grab to
removal concrete structure.
Underwater remote controlled diamond wire cutting machine to remove raked piles.