DEMOLITION OF EXISTING JETTIES AT  TUAS CRESCENT

Country:   Singapore

Client:  Damen Shipyards (Singapore)

Start date:  June 2021

End date:  September 2021

Scope:  Demolition of existing foreshore structure.
Jetty Pier 1 (8mx5.5m)
Jetty Pier 2 (12mx5.5m)

Challenges:  Concrete removal : approximately 600m3
Removal of Existing Spun Piles (Dia 700mm)
Total: 70nos (raker piles : 11nos)