LIGHT SHOW AT MARINA BAY

Country:   Singapore

Client:  Marina Bay Sands

Specialist:  Aquatic

Start date:  October 2016

End date:  May 2017

Scope:  Design & Build custom-shape steel pontoons
Design & build 12m glass prism
Installation of pumps and floating frames
All electrical works

Challenges:  Restricted access to site
All site works to be completed within 3 months  shutdown
Unconventional 12m high glass
pod to install on floating platform